logo Sálim Ali Foundation

Athirappilly Issue - Background & Timeline

The Kerala State Electricity Board (KSEB) proposes to construct a hydro-electric dam across Chalakudy River in Trichur district, Kerala to generate 163 MW of power (233 Mu firm energy) to meet the deficit during the peak hours from 6 pm to 10 pm. The revised estimated cost as per the 2004 PWD schedule is about Rs. 385.63 crores,currently it is estimated at 650 cr..

In May 1996 KSEB appointed Tropical Botanical Gardens and Research Institute (TBGRI) to conduct an Environmental Impact Assessment (EIA) without going for limited quotations and asks for report submission within 8 months of the date of order. In October 1996, the KSEB sent the TBGRI EIA report to MOEF claiming that the study has taken almost one year while the study had commenced only after May 1996.

The Ministry of Environment and Forest, Government of India gave environmental clearance on 20.1.1998 and forest clearances on 22.12.1997 (Stage I - Forest Clearance) and on 16.12.1999 (Stage II Forest Clearance).

In response to three Public Interest Litigations, protesting the irregularities in the procedure followed for tendering and the clearance of the dam by the MoEF (violating the Environmental Protection Act), the honourable High Court of Kerala suspended the above sanction and asked the KSEB to re-examine the procedure. It directed the Central Government to withdraw the sanction and conduct a public hearing in accordance with the EIA notification of the MoEF (1994) and the amendment to it dated 10.4.1997 (Kerala High Court judgment dated -17.10.2001) and only then reconsider the grant of Environmental Clearance.  

Accordingly, a public hearing was conducted by the Kerala State Pollution Control Board on 6.2.2002 at Trichur. It was attended by around 500 people who summarily rejected the project. It was convincingly brought out that the EIA was incomplete. The report submitted by the Public Hearing Panel asked for a second comprehensive EIA that included inter alia consultations with local bodies, various departments of the government and the local communities of the river basin.

In March 2004, the media reported that the KSEB has already got the second EIA done through the Water and Power Consultancy Services (India) Ltd. (WAPCOS), and that the KSEB was trying to approach the MoEF for final clearance.

Inquiry with the public in the proposed project area, local bodies and various departments of the government revealed that they were not aware of any such studies and that nobody had had any discussions with them.

The Chalakudy River Samrakshana Samithi, one of the petitioners to the High Court, approached the Kerala State Pollution Control Board through legal channel and obtained a copy of the report.

It was found that this second EIA report was not comprehensive either, and that the methods followed for the biodiversity studies were unscientific and unacceptable. There was a conscious effort to suppress vital information to support the project. There was no indication that the WAPCOS had any consultation with the agencies suggested by the Public Hearing Panel. (Comments on the EIA).
 
However, the KSEB went ahead with the move to obtain the clearance from the MoEF. This clearance was granted by the MoEF on 10.2.2005, not withstanding the numerous flaws in the EIA.  It may be noted that though it was only on the demands of the public that the second EIA was conducted, the report was not made publicly available.

Immediately, another PIL was filed by the Athirappilly Grama Panchayath and the tribals, possibly the most impacted sufferers of the proposed dam, challenging the sanction accorded by the MoEF on the grounds that the second EIA report was not publicly circulated or made available, and that there was no public hearing on the findings of the second EIA report.

The honourable Division Bench of the High Court of Kerala by its order dated 23 March 2006 overturned the Environmental Clearance given by the MoEF and asked the Kerala State Pollution Control Board to conduct a Public Hearing after “publishing the environmental assessment report stated to have been prepared by the KSEB”.

Thus, the second Public Hearing on the proposed Athirappilly hydro-electric dam was conducted on 15 June 2006 at Chalakudy, Trichur. More than 1200 people attended the Public Hearing.  Only 63 people could speak. Except an employee from the KSEB who presented the project, none spoke in favour of the project. Not only that, all of them vehemently opposed the project on various grounds. The entire audience approved each point raised by each speaker against the project. 

Moreover, in the 252 written representations submitted to the Public Hearing Panel, the ratio for and against the project was 1:9 respectively.

It is conspicuous from the minutes of the Public Hearing Panel that the members were not in agreement with the draft minutes.  Three of the members dissented and two of them jointly submitted another report. And these two happened to be the Presidents of the Athirappilly Gram Panchayath and the Chalakudy Block Panchayath; representatives of the people of the two panchayats who would be affected directly by the construction of dam.

Therefore, it is beyond any doubt that the local people are totally against the project

 A thorough analysis of the EIA report prepared by the WAPCOS shows that the EIA is a total farce. Even the duration of the study is doubtful. It is stated that the EIA was conducted from January to December 2002. But the demand for the second EIA was made only at the Public Hearing held on 6 February 2002! Moreover, no data on biodiversity have been given showing monthly or seasonal variations.

Although the methodology used in the EIA for documenting the biodiversity is totally unacceptable, the statistically unacceptable smallest ever samples reported in the EIA also show how unique the area is in terms of endemic and threatened species. Had WAPCOS followed standard methods, these would have been several times more.

One is at a loss to understand the reasons for:

a)  the KSEB to get the second EIA done by the WAPCOS in such a secret way; even without the knowledge of the tribals who live inside the project area;

b)  the MoEF to accept such an incomplete, unscientific report;

c)  granting permission for the project even with out having the mandatory Public Hearing on the second EIA;

d) WAPCOS failure to have consultations with the local scientific institutions and bodies, concerned government departments and local communities; (even the forest department was not consulted)

e) ignoring the unanimous view of the Public against the project as expressed at the Public Hearing ,

f) observations made by the Public Hearing Panel against the unanimous  apprehensions of the public (I understand it was beyond the mandates of the Public Hearing Panel.) and, finally

g)  the unusual way the minutes of the Public Hearing Panel got signed from the members. The signatures are in 5 sheets; the Member Secretary and the District Collector have signed in all the sheets. Others put their signature in different sheets! One member, the Additional Secretary to Government of Kerala, (Power Department) has not signed in any of the five sheets.

On the EIA, even the Honourable High Court, in its judgment mentions that “the EIA stated to have been made”. Why was such an EIA not rejected by the Expert Committee for River Valley Projects of the MOEF is a matter of serious concern.

We now understand that the Expert Committee of the MOEF on the River Valley Projects met on 15 November 2006 and has recommended the project with some conditions.

We urge you, as a responsible citizen, to consider these points (also see “What will be the loss due to the dam?”) and play an active role to save this ecologically sensitive ecosystem from the impending disaster.  Click here to see how you can contribute.

Timeline of the campaign against the proposed Athirappilly hydro-electric project*

1980s: First news about the proposal of a  dam

1986: The Chalakudy Puzha Samrakshana Samithi (CPSS) is formed for studying the river basin and the various threats faced by it. Athirappilly HEP appeared  as  the first major threat.

1989: The project proposal reaches the MoEF for Environmental Clearance, but it refuses the clearance for the following reasons

  1. Loss of teak plantation and forest rich in biological diversity
  2. Loss of habitats of wild elephants and some endangered species.
  3. Extinction of the aquatic life downstream of the reservoir.
  4. The Athirappilly falls would remain dry for the entire duration. Thus the area would be deprived of its natural scenic tourist spot which cannot be recreated

 

1994: The EIA Notification 1994 of the MoEF comes into force thereby EIA becomes mandatory for clearance

1996: TBGRI (Tropical Botanical Garden and Research Institute) based in Thiruvananthapuram is entrusted with carrying out Rapid EIA for the project. They carry out a Rapid EIA during monsoon  while the EIA notification says that a REIA (Rapid Environmental impact Assessment ) shall be carried out only during non-monsoon .

1997: EIA Notification Amendment 1997 makes Public Hearing Mandatory to large projects

1998: The CPSS submit a petition against the project in the World Commission on Dams (Author(s): Unnikrishnan, S. Serial No: SOC012, WCD Report 2000)

1998 January 20: The MoEF gives the Environmental Clearance without having a  Public Hearing.

1998: Kerala State Electricity Board gives consultancy to SNC Lavalin, a Canadian Company to prepare a Bankable Report of the proposed Athirappilly HEP. SNC Lavalin submits its report in August 1998.

1999: Kerala State Electricity Board prepares a new Detailed Project Report based on the recommendations of SNC Lavalin.

2000 December: People in the river basin come to know through media reports that the project has obtained clearance from the MoEF and the work would start in January 2001.

2001 January: The Secretary, MoEF along with Dr.V.S.Vijayan, Director, SACON, visit the project area where the CPSS explains the project details and probable impacts.
The Chalakudy Puzha Samrakshana Samithi files a PIL in the High Court of Kerala challenging the REIA, the quality of the report and grant of Environmental  Clearance to the project based on the scientifically unacceptable REIA.

2001 January onwards, CPSS gradually starts campaign amongst the river basin grama panchayaths, and tribes. Just three members from the Samithi were actively involved in the initial campaign.

2001 March: The KSEB decides to cut down the forests in the project area. Immediately another downstream group, ‘Nilanilpu’ based in Kodungallur, moves a PIL in the High Court of Kerala.

2001 October 17 : The High Court of Kerala passes a judgment suspending the Environmental  Clearance. The excerpts from the judgment; “We direct the Board to comply with the requirements of Environment Impact Assessment Notification, 1994 as amended by the notification of 1997 in so far as it relates to public hearing and direct the Board to send up to the Authority concerned the report of public hearing also as mandated by the amended notification. We direct the Central government to reconsider the question of grant of environmental clearance in terms of the Environment Impact Assessment Notification, 1994 as amended by notification dated 10-4-1997 on the basis of all the materials including the report of public hearing. Till fresh decisions are taken on these two aspects, the finalisation of the contract and the starting of the work will stand suspended or stayed and the finalisation, construction and commissioning will abide by the result of the reconsideration ordered.
During the course of the hearing, it was revealed that the Hydro Electric Projects already commissioned by the Board and managed by it are not producing energy as planned and the generation of electricity has fallen far short of the anticipated or expected production. It is also brought out that there is considerable loss in transmission and also by way of theft. Taking note of the submissions made by counsel for the petitioners, Standing Counsel for the Board and the learned Advocate General that the State is badly in need of additional power, it appears to us that the first step to be taken by the Board is to take up the rectification or repair works in the Hydro Electric Projects so as to restore the optimum generation of energy in those projects and also to take steps to minimise the transmission loss and eliminate theft of energy. Since we are concerned with public interest in these proceedings, we think that it is just and proper to issue a direction to the Board to take all the necessary steps to repair and restore to full capacity, all the existing Hydro Electric Project to ensure that the generation of power as envisaged is obtained and also to take steps to ensure that transmission losses are minimised and that theft of energy is prevented and to the extent possible eliminated altogether. There will be such a direction to the Board”

2002 February 6 : The first Public Hearing on the Project at Trichur;   attended by more than 500 people including farmers, tribals, students, housewives, merchants, and voluntary organizations from  the river valley and, experts from the field of ecology, fisheries , agriculture as well as students. The public out rightly reject the project. The Public Hearing Panel recommends a comprehensive EIA covering all the seasons and a fresh public hearing on the Comprehensive EIA. The panel insisted on the participation of downstream local bodies, other departments and NGOs in the new EIA.

2002: March – November: CPSS start reaching out to the grama panchayaths in the river basin and take the issue beyond the river basin to other states.

2002 December: CPSS members attend the World Commission on Dams Nepal program where the Athirappilly issue was presented.

2003 January: CPSS members attend the Asian Social Forum held at Hyderabad where Athirappilly issue was raised at an EIA meeting organized by Environmental Support Group, based in Bangalore.

2003 February: CPSS member attends a two day workshop organized by the Wageningen University, Netherlands and the National Institute of Rural Development, Hyderabad on ‘Deliberative Democracy’ where the Public Hearing as a platform for raising concerns at river basin level becomes a theme paper.

2003 November: CPSS member attends the Second International Meeting of Dam affected and their Allies held in Rasi Salai, Thailand along the banks of the Pak Mun River which had an ongoing struggle against dams. An exhibition on the Athirappilly issue was held at the venue.

2005 February 10: The Project again obtains  Environmental Clearance based on a new EIA by WAPCOS (Water And Power Consultancy Services (pvt) Ltd). We come to know of  this through the newspapers. Local people or panchayath was not aware of the new EIA.

2005 April: Athirappilly Grama panchayath and a Kadar tribal leader file PILs in the High Court of Kerala challenging the new clearance granted by the MoEF on the basis of an EIA conducted with out their knowledge and not considering their survival issues associated with the construction of dam

May 2005: CPSS organizes a People’s Public Hearing in protest against the KSEB not holding the mandatory Public Hearing. Noted environmentalist Prof M.K.Prasad presides as Chairman of the PH. More than 250 people attend.

June 2005: Around 40 local and state level organizations decide to join the struggle to save the Chalakudy river and, the Chalakudy River Protection Forum (CPF) is born.

2005: A river walk from 23 – 26 November ending with  a Convention on Water Rights in the Athirappilly Grama Panchayath  was conducted. Inaugurated by Sri.K.P.Rajendran M.L.A and keynote address delivered by noted writer Prof. Sarah Joseph, the convention was attended by more than 500 people.
 
2005 December 23: The State Government decides to lay foundation stone for the proposed project . The  CPF begins satyagraha from 23 December which continued up to ------.

2006 March 23 : The High Court of  Kerala quashes the Environmental Clearance granted by the MoEF in February 2005, orders a new Public Hearing and directs the K S E B to apply afresh for the Environmental Clearance.

2006 June: At the High Court ordered Public Hearing, more than 1200 people represented by tribals facing displacement, Vana Samrakshana Samithi members of the area, farmers living downstream of the project area, experts in ecology, fisheries, wildlife, ornithology, and  students, gather and again reject the project summarily

2006  August: The report of the Public Hearing panel goes to the MoEF. The River Valley Committee meets, but does not take a decision and asks for certain clarifications from  the KSEB.

2006 October 9: A mass signature campaign at river basin level starting from Chalakudy town is organized against the project.

2006 December 3: Support groups are formed in Trichur and Kochi Corporations and programs planned in support of the struggle to save the Chalakudy river.

2006 December 6: A 20 member CPF team visits the Chief Minister in Thiruvananthapuram and submits the signatures of more than 40,000 people opposing the dam. The Honorable CM listens to  five representatives of the team which includes the tribal chieftain of the Pokalapara settlement facing displacement, Ammini and Janaki from Vana Samrakshana Samithi of Athirappilly. A support group is formed in Thiruvananthapuram.

2006 December 18 : A half day dharna is organized at the Kerala Government Secretariat Office attended by many Thiruvananthapuram based organizations such as Thanal, Greens, and SYM .

2006 December 22: A sitting of the Kerala State legislative Committee on Environment slated at Athirappilly Community Hall based on a submission from Chalakudy Puzha Samrakshana Samithi has been postponed.

2006 December 23: First Anniversary of the Indefinite Satyagraha is held at Athirappilly, the Satyagraha venue.

2006 December 28: A dharna (sit in) is organized at the KSEB office Thrissur jointly by the Support group in Thrissur and CPF.

2007 January 13: An open debate on the power crisis in Kerala is held from 3 p.m. to 7 p.m. Inaugurated by Sri.Madhusoodhanan Pillai IAS, Director, World Institute on Sustainable Energy, Pune, the debate was attended by well known social activist C.R.Neelakantan, KSEB officials, and members of the All Kerala River Protection Council.
 
2007 January 18: A massive rally participated by around 600 people march to the KSEB office in Chalakudy town and register their protest against the dam. The rally meeting is inaugurated by famous activist Ajitha.

* This note was prepared by CPSS

About Us | Contact Us | ©2007 Sálim Ali Foundation This site is optimized for Firefox